CLEAN AIR ACT
NOTICE OF INTENTION TO
CONSTRUCT A CONTROLLED PLANT
Pursuant to Part II of the Clean Air Rules 1993,
application has been made to the Environmental
Authority for a permit to construct a controlled plant as follows:
NAME OF APPLICANT
Bermuda Electric Light Co. Ltd
ADDRESS OF THE PROPOSED
CONTROLLED PLANT
North Power Station site
27 Serpentine Road
Pembroke HM 07
DESCRIPTION OF PROPOSED
CONTROLLED PLANT
One 100 cubic yards per hour concrete batch plant.
This application is available for inspection at the
Department of Environment and Natural Resources
during normal working hours. Any person wishing to
object to the proposed plant may, within 14 days of
the date of this publication, lodge their objection with
the Department of Environment and Natural Resources,
169 South Road, Paget DV 04. Letters of objection must
state the name and address of the objector; the grounds of the objection;
whether the objector has an interest in land near to that which the application
relates; and be signed by the objector.
DATE: 25 February 2019