  • The Ministry of Public Works is advising that effective August 6, 2018, Blackwatch Pass will be closed to traffic so that construction works can be conducted. The closure will be for an extended period of time. While Blackwatch Pass is closed the public is encouraged to seek alternative routes to avoid delays.

Alerts

  • The Ministry of Transport and Regulatory Affairs is advising that beginning Friday, August 10 the Central Bus Terminal ticket kiosk in Hamilton will operate on an amended schedule. Read more

Construction of retaining wall and sidewalk construction at #2 industrial park road, southampton

Project Number:

HW 89993
Open/Closing Date:
Friday, November 20, 2015 - 05:00 to Friday, December 11, 2015 - 11:00

Status:

Closed

Type:

Works

Executive Summary:

Tenders are invited from experienced General Contractors for the above captioned project. The project involves all works required for the construction of a 1.2 metre high reinforced concrete block retaining wall and a 1.4 metre wide kerbed concrete sidewalk and associated works on Industrial Park Road and Middle Road at #2 Industrial Park Road.

Contractors submitting a tender for this work will be required to provide sufficient information to demonstrate their technical and financial capability to complete the works in accordance with the specification and contract drawings.

A site visit can be arranged by contacting Carolina Drew at 297-7999, email codrew@gov.bm

RELEASE DATE: Friday, 20 November, 2015
DEADLINE FOR SUBMISSION OF PROPOSAL DOCUMENTS: Friday, 11 December, 2015 no later than 3:00 p.m. Atlantic Daylight Time (ADT)

Awarded to:

Brown and Company Ltd.

Total Value:

$74,149.00

Date Awarded:

Tuesday, May 31, 2016