Public Access to Information Act 2010 –Sect. 6 (6) (Contracts valued at $50,000 or more)
Bermuda Land Development Company Limited
This Notice applies to the contracts contained in the following Table:
No. |
Name of Contractor |
Contract Start Date |
Contract End Date |
Description of Goods / Services Provided |
Contract Value |
Island Construction Services (ICS) |
21 Feb 2022 |
15 Dec 2022 |
Water and Wastewater Infrastructure Project: TP#3A - Sanitary Sewer Force Main - Southside Area East |
$1,346,196 |
|
2 |
Invisible Trenching |
2 Feb 2022 |
30 Jan 2023 |
Water and Wastewater Infrastructure Project: TP#3B - Sanitary Sewer Force Main - Southside Area West |
$1,090,253 |
3 |
H&H Plumbing & Mechanical |
14 Mar 2022 |
13 Jan 2023 |
Water and Wastewater Infrastructure Project: TP#4 - Southside Wastewater Treatment Facility Plant Upgrades and Phase I Telemetry |
$1,480,136 |
4 |
Alternate Concrete Solutions |
3 Mar 2022 |
30 Jan 2023 |
Water and Wastewater Infrastructure Project: TP#5A - Potable and Reclaimed Water Reservoir Transfer Network East |
$1,148,845 |
5 |
Smith Excavating |
25 Feb 2022 |
30 Nov 2022 |
Water and Wastewater Infrastructure Project: TP#5B Potable and Reclaimed Water Reservoir Transfer Network West |
$1,277,177 |
6 |
Burrows Plumbing Services |
31 Oct 2022 |
26 Jan 2023 |
Water and Wastewater Infrastructure Project: TP#5C.1 Potable and Reclaimed Water Reservoir Transfer Network Pumps and Controls |
$520,000 |
7 |
P&M Electrical Ltd |
2 Nov 2022 |
30 Jan 2023 |
Water and Wastewater Infrastructure Project: TP#5C.1A Potable and Reclaimed Water Reservoir Transfer Networks - Pumps and Controls (Electrical Work Only) |
$388,120 |
8 |
Richardson & Wright Construction |
14 Sept 2022 |
13 Jan 2023 |
Water and Wastewater Infrastructure Project: TP#5C.2 Construction of two (2) New Reservoir Pump Buildings No. 9 and No. 13 |
$232,550 |
9 |
Burrows Plumbing Services |
17 Oct 2022 |
14 Dec 2022 |
Water and Wastewater Infrastructure Project: TP#5C.3 - Reservoir #3, Mechanical Demolition, Modifications and Civil Works |
$110,720 |
10 |
P&M Electrical Ltd |
8 Dec 2022 |
21 Dec 2022 |
Water and Wastewater Infrastructure Project: TP#6A - Electrical Infrastructure for Southside Force Mains |
$293,180 |
11 |
GASVODA (Grundfos) |
Nov 2021 |
May 2022 |
Water and Wastewater Infrastructure Project Basins, Pumps and Control panels |
$2,995,070 |
12 |
Milhouse Engineering |
|
|
Water and Wastewater Infrastructure Project Program Management Services and Design |
$1,470,029 |
December 20, 2022